To apply for a road work permit, please visit the Customer Portal.
Select the appropriate application type, complete the form and submit the required supporting documents.
You must obtain a Regional Work Permit for any work taking place on a Region of Waterloo Road.
Supplemental Information
The following information is required with a road work permit submission.
- A Traffic Control Plan will be required with submission. Traffic Control Plans must adhere to Ontario Ministry of Transportation Book 7.
- A Certificate of Insurance (COI) with $5,000,000 in insurance with the Township of Woolwich listed under “additionally insured”.
- A Site Plan detailing the work that is to be completed
Damage Deposit
Township staff will review your road work permit application and decide whether a damage deposit is required. A damage deposit ensures that the right-of-way is restored to its original condition. Township staff will determine the risks to municipal infrastructure and any potential liabilities to determine whether an insurance requirement is needed.
If a damage deposit is required, it must be submitted before any work begins. The applicant is responsible to request the Township to complete an inspection after work has been completed.
Processing Time
The application review process for a Road Work Permit takes a minimum of 10 business days.